SOUTH AFRICA – State utility Eskom, which supplies almost all of South Africa’s electricity from coal-fired power plants, is considering spending R106 billion (US$7.3 billion) investment on wind and solar energy by 2030.

The investment plan, which Eskom could carry out by itself or in partnerships, is the most detailed demonstration yet of the utility’s ambition to move away from coal by taking advantage of the nation’s abundant wind and solar resources. 

The state-owned company envisages spending R61.75 billion (US$4.2 billion) on wind power and R44.25 billion (US$3.03 billion) on solar energy by the end of the decade, a company presentation as reported by Bloomberg.

Some of the projects are planned on the sites of coal-fired plants that are scheduled to close.

The firm confirmed the presentation and the costs without giving further detail.

The potential investment is part of a plan previously communicated by Chief Executive Officer Andre de Ruyter to borrow money from development-finance institutions for projects that would reduce emissions from a company that accounts for two-fifths of South Africa’s greenhouse gas output. 

While President Cyril Ramaphosa has set up a commission to advise him on climate change, Eskom’s plans have been publicly opposed by Gwede Mantashe, his energy minister, who says such a transition could eliminate thousands of coal-dependent jobs.

The presentation outlines three phases for the investment once funding and regulatory approvals have been secured. 

In the first phase, which would span from 2022 to 2023, 246 megawatts of photovoltaic solar power could be built at the Arnot, Duvha, Lethabo, Majuba and Tutuka coal-fired power plants and a further 100 megawatts of solar-generation capacity could be built at Komati, the first of the aging power plants slated to close, and 19.5 megawatts of solar power at the site of the Sere wind-power plant.

Concentrated solar

The second phase, which would last from 2023 to 2025, could see the construction of a 750 megawatt concentrated solar power plant at Olyvenhoutsdrift in the Northern Cape and 600 megawatts of photovoltaic power added at Sere. 

The company may also seek to build 300 megawatts of wind power at Kleinzee on South Africa’s northwest coast and 200 megawatts of wind power at Aberdeen in the Eastern Cape province.

A further 250 megawatts of renewable energy generation capacity could be built on the sites of decommissioned coal-fired power plants. 

The third phase envisages the building of a further 2,950 megawatts of solar photovoltaic capacity between 2025 and 2030 as well as 3,100 megawatts of wind power.

Eskom already has a debt of about R400 billion (US$27.4 billion), mainly from an overrun in the cost of construction of two coal-fired power plants.

Debt from development-finance institutions is generally cheaper than borrowings from commercial lenders.

 

Liked this article? Subscribe to DealStreet Africa News, our regular email newsletter with the latest news, deals and insights from Africa’s business, economy and more. SUBSCRIBE HERE